Question

Ziker Golf Company is evaluating a capital budgeting project that has a higher risk than the average risk of its existing assets. When evaluating projects that are riskier than average, Ziker normally adjusts its required rate of return by 4 percent. Ziker requires a 12 percent return on average-risk projects. What required rate of return should Ziker use to compute the net present value (NPV) of the risky project it is currently evaluating?

a. 8%

b. 12%

c. 16%

d. 10%

e. 48%

Answer

This answer is hidden. It contains 1 characters.