Question

You have been assigned a line balancing task and given a list of tasks, their precedence requirements, and the time needed to accomplish them. As you begin to balance the line, you realize that you must make some assumptions. What are these assumptions and which of them has the greatest impact on the success of your balance?

Answer

This answer is hidden. It contains 541 characters.