Question

You are given the following information about activity F:


Normal time = 16 weeks
Crash time = 10 weeks
Crash cost = $45,000
Cost to crash per week = $2,000

What is the normal cost for activity F?

A) greater than or equal to $55,000

B) less than $55,000 but greater than or equal to $47,000

C) less than $47,000 but greater than or equal to $40,000

D) less than $40,000

Answer

This answer is hidden. It contains 58 characters.