Question

You are given the following information about activity B:


Normal time = 9 weeks
Crash time = 5 weeks
Cost to crash per week = $2,000
Crash cost = $41,000

What will it cost to complete activity B in 6 weeks?

A) less than or equal to $34,000

B) greater than $34,000 but less than or equal to $36,000

C) greater than $36,000 but less than or equal to $38,000

D) greater than $38,000

Answer

This answer is hidden. It contains 58 characters.