Question

You are given the following information about activity A:


Normal time = 9 weeks
Crash time = 7 weeks
Normal cost = $20,000
Crash cost = $30,000

What will it cost to complete activity A in 8 weeks?

A) less than or equal to $24,000

B) greater than $24,000 but less than or equal to $27,000

C) greater than $27,000 but less than or equal to $30,000

D) greater than $30,000