Question

Why are activities drawn in a serial relationship in a network diagram?
a. The activities use different resources.
b. The activities are independent of each other.
c. From a technical standpoint, the activities must be performed in that sequence.
d. The order of completion doesn't matter.

Answer

This answer is hidden. It contains 1 characters.