Question

Which statement on MRP explosion is best?

A) It calculates the total number of subassemblies, components, and raw materials needed for each parent item.

B) It calculates the total number of raw materials to be purchased from all suppliers.

C) It calculates the total number of parts to be produced for each parent item.

D) It calculates the total number of parts needed to be produced less the number of parts on hand for each parent item.

Answer

This answer is hidden. It contains 110 characters.