Question

Which scheduling tool shows the necessary sequence of activities in a project and identifies the critical path?

A) Gantt chart

B) Process flowchart

C) Detailed schedule

D) Master production schedule

E) PERT chart

Answer

This answer is hidden. It contains 27 characters.