Question

Which one of the following statements about the time study method is true?

A) It is most appropriate for "thinking" jobs such as an automobile mechanic's diagnosis of a problem.

B) It is used most often for setting time standards.

C) Using the time study method technique, time standards can be set for new jobs before production begins.

D) Performance ratings are not needed in the derivation of time standards.

Answer

This answer is hidden. It contains 64 characters.