Question

Which of the following statements is NOT true about finite capacity scheduling (FCS)?
A.FCS is an extension of Gantt chart methods.
B.FCS requires that jobs be loaded backward from due dates to determine the capacity required at each work center.
C.FCS assumes that jobs are scheduled through a number of work centers, each with one or more machines.
D.In FCS, attention is paid to scarce resources to facilitate job flow and to improve the performance of the shop.

Answer

This answer is hidden. It contains 71 characters.