Question

Which of the following represents the hierarchy of decisions concerning the capacity of operations ranging from long-term to short-term?
A.Facility planning to aggregate planning to scheduling, respectively.
B.Aggregate planning to scheduling to facility planning, respectively.
C.Scheduling to facility planning to aggregate planning, respectively.
D.Aggregate planning to facility planning to scheduling, respectively.

Answer

This answer is hidden. It contains 93 characters.