Question

Which of the following most closely describes net material requirements in an MRP system?
A. Gross requirements - planned receipts
B. Gross requirements - (on-hand + scheduled receipts)
C. Gross requirements - on-hand + scheduled receipts
D. Gross requirements - planned order releases