Question

Which of the following is true for takt time in a lean system?
A. Takt time should be set at greater than the average demand of the market.
B. Takt time is the period of time available for production.
C. Takt time is used to match supply and demand.
D. Takt is the Japanese word for time.

Answer

This answer is hidden. It contains 108 characters.