Question

Which of the following is the correct equation to solve for the net present value of a project.
A) NPV = CF0 + CF1/(1 + k)1 + CF2/(1 + k)2+...CFn/(1 + k)n
B) NPV = CF0 + CF1(1 + k)1 + CF2(1 + k)2+...CFn(1 + k)n
C) NPV = CF0 - CF1/(1 + k)1 - CF2/(1 + k)2-...CFn/(1 + k)n
D) NPV = CF1/(1 + k)1 + CF2/(1 + k)2 +...CFn/(1 + k)n