Question

Which of the following is not used to derive an item's gross requirements?

A) the MPS for immediate parents that are end items

B) the planned order releases for immediate parents below the MPS level

C) the MPS components that are not purchased items

D) any other requirements not originating in the MPS, such as the demand for replacement parts