Question

Which of the following is a tactic for reducing demand pressure on a process bottleneck?
A. Place a quality inspection point immediately before the bottleneck.
B. Decrease the size of batches run through the bottleneck (assuming setup required).
C. Increase inventory levels at the non-bottleneck resources.
D. All of the above.