Question

When the budgets for all the work packages are summed,
a. they should exceed the amount of funds available.
b. they cannot exceed the total project budgeted cost.
c. if the total is too high then the amounts should be force-fitted into the customer's budget.
d. if the total is too low then extra non-project expenses should be added.