Question

When evaluating work packages that have a negative cost variance, you should focus on taking corrective actions to reduce the costs of:
a. activities that have a small cost estimate.
b. activities that have a moderate cost estimate.
c. activities that have a large cost estimate.
d. all the activities in the project.