Question

Use the information in the table and sequence the six jobs using SPT and EDD. Calculate the average flow times and average lateness. All jobs arrived at time zero and are ready at time zero.


Job Production Time Due Date
A 10 20
B 15 25
C 17 22
D 20 31
E 16 20
F 20 24

Answer

This answer is hidden. It contains 178 characters.