Question

Use the information in Scenario 11.1. If item C has a manufacturing lead time of two weeks, and a planned receipt of 65 units is needed in week 4, which of the following statements is true?

A) The planned order release in week 2 for item C is 130 units.

B) The gross requirements for item B in week 4 is 65 units.

C) The gross requirements for item B in week 2 is 130 units.

D) The gross requirements for item B in week 2 is 65 units.