Question

Use the following information to answer the following question(s).
Below are the expected after-tax cash flows for Projects Y and Z. Both projects have an initial cash outlay of $20,000 and a required rate of return of 17%.

Project Y Project Z
Year 1 $12,000 $10,000
Year 2 $8,000 $10,000
Year 3 $6,000 0
Year 4 $2,000 0
Year 5 $2,000 0

Discounted payback for Project Y is:
A) three years.
B) 3.14 years.
C) four years.
D) two years.

Answer

This answer is hidden. It contains 1 characters.