Under a lean thinking philosophy, which of the following would LEAST likely be considered waste?
A. Effort spent sorting defective parts out of a supplier delivery.
B. Customers waiting to be served.
C. Stopping the production line due to a quality problem.
D. Producing a small percentage extra to protect against unexpected problems.