Question

Tim usually exhibits an 80% learning rate for the mechanical tasks he undertakes. His next big project, the fence along the street, will require 35 iterations of the fencepost task. If he has 80 hours available to work on the project, how fast must he perform the first iteration in order to finish all 35 within his allotted time? Refer to the copy of Table I.1 appended to this exam.