Question

There is a 20% probability that the NPV of a project will be $20 million, a 50% probability that it will be sold for $45 million and a 30% probability that it will be for $15 million. What is the expected NPV of the project?
A) $17.5 million
B) $45 million
C) $31 million
D) $26.67 million