The work packages are at a level at which the wants to monitor and control the budget, and can collect data on actual costs and the value of the work completed during the performance of the project.
a. individual assigned to complete the work
b. project manager
c. contractor's chief financial officer
d. project team

Answer

This answer is hidden. It contains 1 characters.