Question

The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. What are the ES and EF times for Task B now that Task A is complete?
a. ES = 9, EF = 14
b. ES = 7, EF = 12
c. ES = 5, EF = 14
d. ES = 5, EF = 12