Question

The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished?
a. Negative 5 days slack.
b. Positive 5 days slack.
c. Positive 16 days slack.
d. Positive 3 days slack.

Answer

This answer is hidden. It contains 1 characters.