The savvy project manager knew there would be a high demand for finish carpenters in late October, so she started a crew early on one section of the house so they would be available to help elsewhere later on. This project manager is engaging in:

A) resource allocation.

B) resource acquisition.

C) resource scheduling.

D) resource leveling.