Question

The production rate has been steady at 20 units per hour. The average work-in-process inventory at this station is 15 units. What is the average lead time through this manufacturing station?

A) 15 minutes

B) 30 minutes

C) 45 minutes

D) 1.0 hours

Answer

This answer is hidden. It contains 140 characters.