Question

The process batch at the constraint in a drum-buffer-rope system should be:

A) the same size as that at any non-constraint.

B) the same size as the transfer batch.

C) of such a size as to maximize the number of setups for the constraint.

D) of such a size as to improve utilization of the constraint.

Answer

This answer is hidden. It contains 67 characters.