Question

The observer assigned a performance rating factor of 1.15 to the worker and the company employs an allowance factor of 20%. How many more observations must be made in order to develop an estimate of the select time for Element 4 that is within 5% with 95% accuracy?

A) 1

B) 3

C) 5

D) 7