Question

The observer assigned a performance rating factor of 1.10 to the worker and the company employs an allowance factor of 20%. What is the standard time for Element 4?

A) 58.58 seconds

B) 56.23 seconds

C) 46.86 seconds

D) 42.6 seconds

Answer

This answer is hidden. It contains 64 characters.