Question

The observer assigned a performance rating factor of 1.15 to the worker and the company employs an allowance factor of 20%. What is the select time for Element 2?

A) 25.3 seconds

B) 24.29 seconds

C) 20.24 seconds

D) 17.6 seconds

Answer

This answer is hidden. It contains 64 characters.