Question

The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and
a. taking any needed corrective action immediately.
b. leaving the project to self-correct.
c. fast tracking all the activities in the project until the project is ahead of schedule.
d. making sure the critical path doesn't change.