Question

The is the amount that was budgeted to accomplish the work that was schedule to be performed up to that point in time.
a. total budgeted cost (TBC)
b. cumulative budgeted cost (CBC)
c. cumulative actual cost (CAC)
d. cumulative earned value (CEV)