The is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time.
a. total budgeted cost (TBC)
b. cumulative actual cost (CAC)
c. cumulative budgeted cost (CBC)
d. cumulative earned value (CEV)