Question

The gross requirements of a part in an MRP system are determined from
A.net requirements + on-hand.
B.net requirements of the end item.
C.gross requirements of the immediate part.
D.planned order releases of the immediate parent item.

Answer

This answer is hidden. It contains 85 characters.