Question

The gross requirements of a part in an MRP system are determined from:
A. Net requirements + on-hand
B. Net requirements of end item
C. Gross requirements of the immediate part
D. Planned order releases of the immediate parent item

Answer

This answer is hidden. It contains 1 characters.