The forecast was 70 units for the current period while actual demand was 76. The forecast for the next period is 75.8. What is alpha if a simple exponential smoothing forecast method is being used?
A.0.004
.0.967
C.0.040
D.0.097

Answer

This answer is hidden. It contains 93 characters.