Question

The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis.

a. Determine the project cost and duration without crashing.

b. Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.

c. Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.

d. Create a graph that shows project expediting cost plotted as a function of the reduction in project duration.


Activity Normal Time Crash Time Normal Cost Crash Cost Predecessor
A 10 7 2,000 2,600
B 12 8 1,500 2,000 A
C 16 12 2,200 3,000 A
D 8 7 2,500 3,000 B
E 13 10 1,950 2,275 C
F 9 8 800 1,000 D
G 24 29 3,650 4,000 E, F
H 17 14 1,200 1,800 G

Answer