The following table contains a list of activities, with early- and late-start and finish times and crash costs for the network shown in the figure. All start and finish times and crash costs are on a per-week basis. Each activity can be reduced by one week at the most.

a. Determine the uncrashed activity lengths for activities A though K.

b. Determine the minimum completion cost for this project if each week carries a fixed cost of $1,000.


Activity ES EF LS LF Crash Cost/week
A 0 5 0 5 $1,100
B 5 9 13 17 $250
C 5 11 5 11 $1,200
D 0 6 1 7 $350
E 6 10 7 11 $900
F 9 14 17 22 $875
G 11 17 16 22 $1,500
H 11 18 11 18 $500
I 18 26 18 26 $300
J 17 21 22 26 $625
K 26 34 26 34 $750

Answer

This answer is hidden. It contains 1051 characters.