Which of the following statements about critical path method (CPM) is true?
A. It is an example of a variable time project scheduling method.
B. It is well suited when activity times are expected to vary.
C. It is well suited when activity times are fairly constant and can be reduced by spending more money.
D. It is well suited for R&D projects and for scheduling computer systems.

Answer