The final assembly schedule in a lean system:

A) should be developed for each product independent of the process requirements for the other products.

B) strives to create a uniform flow at the work centers in the plant.

C) avoids the use of small lot sizes because they create many production orders and cause confusion.

D) allows daily changes in demand levels, regardless of size, to be incorporated immediately into the work center schedules.

Answer