The estimated duration for each activity must be the total elapsed time,
a. the time for the work to be done plus any associated waiting time.
b. the time for the task plus the planning time for the project.
c. the time required for the work times the number of resources assigned to the project.
d. the time for the task plus the time to review and accept the deliverable.