Question

The ES and EF times are determined by calculating forward, that is, by
a. adding all the times together for the project.
b. working through the network diagram from the beginning of the project to the end of the project.
c. calculating the optimistic and pessimistic times for the project.
d. working through the network diagram from the end of the project to the beginning of the project.