Question

Table 7.14

You are responsible for managing a project with the following activities (times are given in weeks).

Task Predecessor Optimistic Most Likely Pessimistic
A -- 5 8 10
B A 7 10 12
C B 8 10 14
D -- 11 15 20
E D 12 14 18

Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?

A) It will not change.

B) It will increase by one week.

C) It will increase by two weeks.

D) It will increase by three weeks.

Answer

This answer is hidden. It contains 53 characters.