Question

Table 7.9

Using Table 7.9, what is the difference, in dollars, between the minimum-time schedule and the schedule created by crashing all activities to their limits? Assume that there are no indirect or penalty costs.

A) less than or equal to $1,000

B) greater than $1,000 but less than or equal to $2,000

C) greater than $2,000 but less than or equal to $3,000

D) greater than $3,000