Question

Table 7.3

Using Table 7.3, if the project manager wants at least a 98% probability that the project will be completed on or before the due date, what is the shortest project due date that will satisfy the manager?

A) fewer than or equal to 28 days

B) greater than 28 days but fewer than or equal to 30 days

C) greater than 30 days but fewer than or equal to 32 days

D) greater than 32 days