Question

Table 7.2

Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase?

A) fewer than or equal to 2 weeks

B) greater than 2 weeks but fewer than or equal to 4 weeks

C) greater than 4 weeks but fewer than or equal to 6 weeks

D) greater than 6 weeks