Question

Table 10.8

Suppose that the following eight jobs must be scheduled through a car repair facility (repair times are shown in days):

Car Repair Time Due Date
A 3 11
B 10 9
C 7 10
D 12 8
E 4 17
F 15 35
G 8 13
H 9 23

Use the information in Table 10.8 to answer this question. Which job retains the same position in both an EDD and an SPT sequence?

A) A

B) B

C) C

D) G

Answer

This answer is hidden. It contains 54 characters.